Fast React Keywords: Important Notions
Fast React
Keywords: Important Notions
Line Capacity
How many minutes
are available in every hour of each line (calculated by the number of workers
multiplied by 60 minutes)
Line based on 28
workers’, Hourly Capacity in single line
=28*60=1680
minutes. You remember that you will make plan based on garments SAM which is
also the value stands in minute.
There are 2 ways
of setting the capacity.
1) Fixed Capacity – Most Suitable for line producing same product over the
year. Small industry, like producing T-Shirt over the year in same floor can
use same configuration, no need adjustment.
2) Flexible
Capacity – applicable for line configurations that changes based on the product
type. More for factories with a bigger product mix.
Critical Path
This is a list of events which must happen for
the order to begin e.g. Sample approved and order fabric. This does not include
production operations (also known as Time & Action). Before start bulk
production each event needs to complete on time.
Event name
The name of the critical path event:
Sample approval
Sewing thread in house
Fabric in house
PP Meeting
Trial Run
complete
Lead time
In fast react, lead time is the time line of
any event need to complete determiner.
Ex: If sample approval is required 10 days
before bulk cut, 10 is Lead time of this event. which is also call offset.
Relative to
This is the point in the plan that we use to
count from when applying lead times in critical path e.g. start cut, first
output date
Target (Event Complete)
Date= Relative to + lead time (or offset)
Executive
Individual responsible to manage each segment,
like low level planning, CPM, high level planning management.
Expected Date
When event target date is not achievable, possible completion date can be entered. Example: Fabric receive target date is 5 January. However, due to supplier delay fabric will be received on 7 January. This date need to enter on Expected date so that all relevant personnel get the latest update.
Retained Date
Agreed target date. This date is manually saved once target dates are agreed with relevant stakeholders. Retained date is required when target date is generated based on production plan.
When event target date is not achievable, possible completion date can be entered. Example: Fabric receive target date is 5 January. However, due to supplier delay fabric will be received on 7 January. This date need to enter on Expected date so that all relevant personnel get the latest update.
Retained Date
Agreed target date. This date is manually saved once target dates are agreed with relevant stakeholders. Retained date is required when target date is generated based on production plan.
Group
You can separate production lines into groups
for easier reporting and visibility e.g. separation could be by product type,
woven lines, knit types, location and production method etc
Learning curves
An allowance that can be set in the plan to
reduce output over the first few days of a new style/ order (also called start
up allowances or style change allowances).During changeover new product like
T-Shirt to Hoody need to consider Efficiency trend 30%,45%,50%,55% day
1,day2,day2 day4 sequentially. Fastreact has pre-build and also modifiable
learning curve parameters in which Efficiency trend and output can be adjusted.
Planning board
The tool within Fastreact which enables you to
have visual status of your orders
Line
This is the row
name or line name in a group on your planning board
Product
Style: T-shirt, Jacket, hoody, Pants, Leggings
Product type
Style type e.g. basic polo shirt, 5 pockets
western jean etc
Product type
efficiency
The percentage of which a particular product
type is able to be made on a certain line
SAM
Standard Allowed Minutes per garment (how long
it takes to produce 1 garment in that operation). This is the same as SMV also.
Standing time
It is the time in days an order takes to pass
through each required operation e.g. if we cut 3 days before we start to
embroider then the cutting standing time is 3 days.
Timetables
Critical path is specific to a certain
situation e.g. Nike new order with 90 lead time will have certain events
whereas an Adidas repeat order with a 30-day lead time will have different
events and executives. This are the list of events need to perform before start
the production
Throughput days
Time taken from first feeding a sewing garment
into a line to first feeding garment out of a sewing line.
User defined fields
Any extra information you may require which
Fastreact does not originally have relating to orders or products. These can be
text or numeric e.g. Buyer PO number, season etc
WIP
Work in Progress e.g. the amount of work in
progress is calculated by the amount completed less the amount produced by the
previous operation e.g. Cut 2000 pieces
but only sewn 1500 pieces the WIP at sewing is 500 pieces. This is related to
standing time because if we set a standing time of 3 days and my target is to
produce 500 pieces per day it is the same as saying i have a WIP level of 500
pieces x 3 days
Fast Tracking
Changing the Default offset days.
Changing the Default offset days.
Transport method
Road / Sea / Air
Status of order
Confirmed, Projection, Forecast
Efficiency
It measures the
target per day as computed by the system to make it more realistic
4 types of
Efficiencies:
Product Type
Efficiency
Order Efficiency
Strip Efficiency
and
Learning Curve Efficiency